| Date | Event | Lanes | Status |
|---|---|---|---|
| 2026-06-17 | IURC Order in Cause 46322 Approves NIPSCO-Amazon Special Contract and NIPSCO-GenCo PPA on a Partial Settlement; Pricing Terms Held Confidential
3 src Indiana Utility Regulatory Commission (IURC), NIPSCO, NIPSCO Generation LLC (GenCo) | reported | |
| 2025-11-19 | IURC Reaffirms GenCo Approval and Amazon Special Contract Framework; NIPSCO Announces $7B, 2.6GW Gas + 400MW BESS Build for Amazon
5 src NIPSCO, NIPSCO Generation LLC (GenCo), Amazon Web Services, Indiana Utility Regulatory Commission (IURC) | not re-checked | |
| 2025-09-24 | Indiana IURC Approves NIPSCO GenCo as First U.S. Limited-Regulation Utility Affiliate for Data Center Generation (Cause 46322)
5 src NIPSCO, NIPSCO Generation LLC (GenCo), Indiana Utility Regulatory Commission (IURC) | not re-checked |