| Date | Event | Lanes | Status |
|---|---|---|---|
| 2025-11-19 | IURC Reaffirms GenCo Approval and Amazon Special Contract Framework; NIPSCO Announces $7B, 2.6GW Gas + 400MW BESS Build for Amazon
5 src NIPSCO · Amazon Web Services | confirmed | |
| 2025-09-24 | Indiana IURC Approves NIPSCO GenCo as First U.S. Limited-Regulation Utility Affiliate for Data Center Generation (Cause 46322)
5 src NIPSCO | confirmed |