PJM Interconnection

PJM Interconnection is named in 3 events across the Capture Cascade Timeline, from 2025 to 2026.

3 events From Nov 1, 2025 To Sep 29, 2026 Open in filter view →
PJM Interconnection on the timeline 3 events · 2016–2026 · click any marker
PJM Interconnection on the timeline20202025PJM Interconnection
DateEventLanesStatus
2026-09-29FERC Accepts PJM Backstop Procurement for Filing, Suspends It Five Months to Feb. 28, 2027 and Sets a Paper Hearing on Cost Allocation, Exit Rules and Collateral 3 src
PJM Interconnection · Laura Swett
confirmed
2026-07-28PJM and its transmission owners ask FERC to pause the large-load show-cause proceeding 2 src
Federal Energy Regulatory Commission · PJM Interconnection
reported
2025-11-01PJM December 2025 capacity auction hits record $333/MW-day; data centers account for 40% ($6.5B) of total $16.4B cost 3 src
PJM Interconnection
confirmed