FERC Accepts PJM Backstop Procurement for Filing, Suspends It Five Months to Feb. 28, 2027 and Sets a Paper Hearing on Cost Allocation, Exit Rules and Collateral
On September 29, 2026 the Federal Energy Regulatory Commission issued its order in PJM Interconnection, L.L.C., 196 FERC ¶ 61,245, Docket Nos. ER26-3380-000 and EL26-108-000. The order says: “we accept the proposed RBP for filing, suspend it for five months, effective February 28, 2027, subject to refund, and establish a paper hearing.” It describes the Reliability Backstop Procurement (RBP) as a “one-time procurement of new capacity” for resource adequacy challenges driven by an influx of large loads, and records PJM’s statement that the RBP aims to procure capacity equal to the 6,831 MW shortfall in the 2028/2029 base residual auction.
The Commission finds that “certain aspects of PJM’s proposal are just and reasonable” and sets paper hearing procedures on cost allocation, Transmission Owner exit rules, and LSE collateral requirements. On cost allocation it says that, on the current record, “PJM has not adequately demonstrated that its proposal is just and reasonable and consistent with the cost causation principle.” It encourages PJM to submit a “new FPA section 205 filing” without delay.
Northern Virginia Electric Cooperative (NOVEC) is a protester, not a finding: the order summarises NOVEC’s argument that its highest possible collateral requirement, estimated at about $1.95 billion, would exceed its total assets, and that it is uncertain whether it could secure $2 billion in collateral.
Chairman Laura Swett wrote in a concurring statement: “This Commission will not be forced into accepting a deeply flawed, eleventh-hour procurement mechanism with billion-dollar implications for consumers.” Chairman Swett and Commissioners Rosner, See and LaCerte each concur with a separate statement, and the order attaches no dissent. Related canon: 2025-11-01–pjm-capacity-auction-record-data-center-40-percent-costs.
Update (2026-10-29, announcement date (PJM’s own news post on its filing)): PJM files an amended backstop proposal with FERC, targeting a March 1, 2027 start
PJM’s own news site says PJM “filed an amended proposal to FERC with the goal of commencing a Reliability Backstop Procurement on March 1, 2027.” It describes “modifications to three elements of the original filing” (cost allocation, load-serving-entity credit requirements and exit responsibilities), and says cost allocation “will be based on Large Load growth between the actual summer peak load in 2026 and the forecast for the 2028/2029 Delivery Year.” This is PJM’s description of its own filing; the filing itself was not read and FERC has not acted on it.
Sources & Citations
The Cascade Ledger. “FERC Accepts PJM Backstop Procurement for Filing, Suspends It Five Months to Feb. 28, 2027 and Sets a Paper Hearing on Cost Allocation, Exit Rules and Collateral.” The Capture Cascade Timeline, September 29, 2026. https://capturecascade.org/event/2026-09-29--ferc-rejects-elements-of-pjm-backstop-procurement-plan-data-center-capacity-shortfall/