| 2026-07-07 | Oregon PUC Unanimously Approves PGE Large-Load Rates: Data Centers Up 29.7%, All Other Classes Down
3 src Oregon Public Utility Commission · Portland General Electric | confirmed | |
| 2026-06-10 | Oregon PUC Delays PGE Data-Center Large-Load Rate Ruling to July; 29% Rate Hike at Issue Under POWER Act
1 src Oregon Public Utility Commission · Portland General Electric | confirmed | |
| 2026-05-07 | Oregon PUC Order 26-154 Approves PGE Schedule 96: Data Centers Pay 29% More, Residential Rates Drop