NIPSCO is named in 4 events across the Capture Cascade Timeline, from 2025 to 2026.

4 events From Sep 24, 2025 To Jun 17, 2026 Open in filter view
NIPSCO on the timeline 4 events · 2016–2026 · click any marker
NIPSCO on the timeline20202025NIPSCO
DateEventLanesStatus
2026-06-17IURC Order in Cause 46322 Approves NIPSCO-Amazon Special Contract and NIPSCO-GenCo PPA on a Partial Settlement; Pricing Terms Held Confidential 3 src
Indiana Utility Regulatory Commission (IURC), NIPSCO, NIPSCO Generation LLC (GenCo)
reported
2026-05-01DOE §202(c) emergency coal-retention order log through May 2026: 43+ orders, ~4.4 GW stalled across 6 plants, D.C. Circuit challenges filed 10 src
Chris Wright, Department of Energy, NIPSCO, Earthjustice and 1 more
reported
2025-11-19IURC Reaffirms GenCo Approval and Amazon Special Contract Framework; NIPSCO Announces $7B, 2.6GW Gas + 400MW BESS Build for Amazon 5 src
NIPSCO, NIPSCO Generation LLC (GenCo), Amazon Web Services, Indiana Utility Regulatory Commission (IURC)
not re-checked
2025-09-24Indiana IURC Approves NIPSCO GenCo as First U.S. Limited-Regulation Utility Affiliate for Data Center Generation (Cause 46322) 5 src
NIPSCO, NIPSCO Generation LLC (GenCo), Indiana Utility Regulatory Commission (IURC)
not re-checked