| 2026-09-29 | FERC Accepts PJM Backstop Procurement for Filing, Suspends It Five Months to Feb. 28, 2027 and Sets a Paper Hearing on Cost Allocation, Exit Rules and Collateral
3 src PJM Interconnection · Laura Swett | confirmed | |
| 2026-06-18 | FERC issues Federal Power Act Section 206 show-cause orders to all six RTOs/ISOs on large-load interconnection — RM26-4-000 rulemaking itself remains un-acted-on
6 src Federal Energy Regulatory Commission · Chris Wright · Department of Energy · Laura Swett | reported | |
| 2026-04-16 | FERC misses DOE-ordered April 30 deadline on large-load interconnection Docket RM26-4-000 — issues Intent to Act order committing to June 2026 action