DateEventLanesStatus
2026-06-10Gov. Abbott directs PUCT to require data centers to fully fund own electric infrastructure; PUCT must act to reduce residential transmission costs by July 31, 2026 4 src
Greg Abbott · Public Utility Commission of Texas · ERCOT
confirmed
2026-03-16PUCT issues draft report in Project 58484 recommending Texas shift from 4CP to multi-peak transmission cost methodology — final rules required by December 31, 2026 4 src
Public Utility Commission of Texas · ERCOT · Greg Abbott
confirmed
2025-06-20Texas Gov. Abbott signs SB 6 — large-load (≥75 MW) interconnection reform; mandatory remote-disconnect / curtailment for entrants post Dec 31 2025; bellwether state model for the federal FERC ANOPR 6 src
Greg Abbott · Public Utility Commission of Texas · ERCOT · Texas Legislature
confirmed
2023-09-06Riot Platforms discloses $31.7M in ERCOT power and demand-response credits for August 2023 — record single-month curtailment payout to a Bitcoin miner 2 src
ERCOT
confirmed
2022-10-12Senators Markey and Warren open congressional inquiry into ERCOT subsidies for Bitcoin miners; cite $9.5M Riot July 2022 payment exceeding Bitcoin revenue; project up to $170M in annual miner payouts 2 src