Tag index

#Ratepayer-Cost-Shift

Events indexed under #Ratepayer-Cost-Shift — 34 entries in the record.

34 events From Sep 24, 2025 To Nov 6, 2026 Open in filter view
Activity over time Events per year
2025 · 3 events2026 · 31 events20252026
DateEventLanesStatus
2026-11-06APS Asks the Corporation Commission to Approve a 25-Year, 1.88 GW Direct Pricing Contract With TSMC 2 srcreported
2026-11-03Georgia PSC Flips to a 3-2 Democratic Majority; It Inherits Georgia Power's Data-Center Dockets, With Customer Names Redacted 4 src
OpenAI
confirmed
2026-10-19Arizona Attorney General Moves to Recuse Corporation Commission Chairman Myers From the APS Rate Case 4 src
Kris Mayes
reported
2026-10-01Michigan PSC Order Holds DTE-Google 80% Minimum Billing Demand, Rejects AG Nessel's 90% and 20-Year Termination Asks 2 src
Michigan Public Service Commission, Google, Dana Nessel
confirmed
2026-09-16Duke's Data-Center Cost Projections Blacked Out of the Consumer Brief Challenging Them, Under Duke's Pending Confidentiality Requests 5 src
Florida Public Service Commission, Duke Energy Florida, Earthjustice
reported
2026-09-16House Passes Ratepayer Protection Act 417-3, but Only Directs States to *Consider* Making Data Centers Pay Grid Costs 3 src
U.S. House of Representatives
not re-checked
2026-08-25Florida PSC Tells Duke Its Data-Center Tariff Is on "Shaky Ground" in First Test of SB 484 Cost-Shift Law 2 src
Florida Public Service Commission, Duke Energy Florida
not re-checked
2026-08-19Oracle Drops Wisconsin PSC Suit, Leaving $100M-Plus Annual Collateral Requirement for Port Washington Campus 4 src
Oracle, Wisconsin Public Service Commission, We Energies, OpenAI
not re-checked
2026-08-11Wisconsin PSC Forces ATC to Restart $1.7B Port Washington Data Center Grid Application; FERC Gap Leaves Ratepayer Cost-Shift Unresolved 2 src
Wisconsin Public Service Commission, We Energies
not re-checked
2026-08-10Nessel and Earthjustice File Appeal Briefs Against MPSC Approval of DTE's Stargate Data Center Contracts 4 src
Dana Nessel, Earthjustice, Michigan Public Service Commission, DTE Energy and 3 more
not re-checked
2026-08-06AG Nessel's Michigan Court of Appeals Brief Names Docket Numbers, Argues DTE's Own Filings Admit a Ratepayer Cost Increase 6 src
Dana Nessel, Michigan Public Service Commission, DTE Energy, Oracle and 3 more
not re-checked
2026-08-06Environmental Groups' Court of Appeals Brief Itemizes What DTE's Oracle Data-Center Contracts Charge Other Customers: $260M Rate Base, ~$40M First-Year Distribution Increase 2 src
Natural Resources Defense Council, Sierra Club, Earthjustice, Michigan Public Service Commission and 3 more
not re-checked
2026-07-31Virginia SCC Orders Dominion to Shift Transmission Costs to Data Centers, Cutting Residential Bill Impact to $0.94 2 srcnot re-checked
2026-07-22Montgomery County MD: 18-Month Data Center Moratorium Advances to Full Council Vote 2 srcnot re-checked
2026-07-15Emails Show Entergy Arkansas Co-Drafted Pulaski County Moratorium That Exempts Its Own $6B Prospective Customer 2 srcnot re-checked
2026-07-15Hochul Signs EO 62 — First Statewide Hyperscale Data Center Moratorium as 20+ Localities Move in One Week 3 src
Kathy Hochul
not re-checked
2026-07-08Lakeland FL 'Project Swan' AI Data Center Draws Bipartisan Opposition, Ratepayer Concerns 1 srcnot re-checked
2026-07-07Oregon PUC Unanimously Approves PGE Large-Load Rates: Data Centers Up 29.7%, All Other Classes Down 3 src
Oregon Public Utility Commission, Portland General Electric
not re-checked
2026-06-30Loudon County TN Commission Votes 6-Month Data-Center Moratorium After Resident Hearing 2 srcnot re-checked
2026-06-26NC DEQ Opens Comment on Amazon $10B Data-Center + Duke Energy Air Permits in Richmond County 2 src
Amazon
not re-checked
2026-06-22Arizona and Illinois Impose Data Center Tax Moratoriums Effective July 1; 300+ Data Center Bills Filed in 30+ States in 2026 4 src
JB Pritzker, State of Illinois, State of Texas, Public Utility Commission of Texas
not re-checked
2026-06-19Oracle sues Wisconsin PSC over credit-rating rule that could shift data-center costs onto ratepayers 3 src
Oracle, Wisconsin Public Service Commission, We Energies
not re-checked
2026-06-17IURC Order in Cause 46322 Approves NIPSCO-Amazon Special Contract and NIPSCO-GenCo PPA on a Partial Settlement; Pricing Terms Held Confidential 3 src
Indiana Utility Regulatory Commission (IURC), NIPSCO, NIPSCO Generation LLC (GenCo)
reported
2026-06-11Data-Center Fiscal Capture Crystallizes Across States: Multibillion-Dollar Sales-Tax Exemptions Blow Holes in State Budgets as the Issue Reaches the Ballot (Lever/Capital&Main/Popular Information cluster) 5 srcnot re-checked
2026-06-10Gov. Abbott directs PUCT to require data centers to fully fund own electric infrastructure; PUCT must act to reduce residential transmission costs by July 31, 2026 4 src
Greg Abbott, Public Utility Commission of Texas, ERCOT
not re-checked
2026-06-03New York Legislature Passes Nation's First Statewide Data Center Moratorium (S.10642); Hochul Decision Pending 4 src
Kathy Hochul
not re-checked
2026-06-02Shapiro Releases Pennsylvania Data Center Incentive Conditions as $2B Sales-Tax Exemption Faces June 30 Budget Fight 3 src
Josh Shapiro
not re-checked
2026-05-07Oregon PUC Order 26-154 Approves PGE Schedule 96: Data Centers Pay 29% More, Residential Rates Drop 2 src
Oregon Public Utility Commission, Portland General Electric
not re-checked
2026-04-30Virginia Enacts HB 892 Mandating SCC Investigation of Dominion Load Forecasting Methodology, Authorizes PJM Coordination 1 srcnot re-checked
2026-03-16PUCT issues draft report in Project 58484 recommending Texas shift from 4CP to multi-peak transmission cost methodology — final rules required by December 31, 2026 4 src
Public Utility Commission of Texas, ERCOT, Greg Abbott
reported
2026-03-13PPL Electric PA PUC Settlement: $275M Ratepayer Rate Hike Plus Large-Load Data-Center Tariff as 20 GW Pipeline Looms 3 srcnot re-checked
2025-11-19IURC Reaffirms GenCo Approval and Amazon Special Contract Framework; NIPSCO Announces $7B, 2.6GW Gas + 400MW BESS Build for Amazon 5 src
NIPSCO, NIPSCO Generation LLC (GenCo), Amazon Web Services, Indiana Utility Regulatory Commission (IURC)
not re-checked
2025-11-01PJM December 2025 capacity auction hits record $333/MW-day; data centers account for 40% ($6.5B) of total $16.4B cost 3 src
PJM Interconnection
not re-checked
2025-09-24Indiana IURC Approves NIPSCO GenCo as First U.S. Limited-Regulation Utility Affiliate for Data Center Generation (Cause 46322) 5 src
NIPSCO, NIPSCO Generation LLC (GenCo), Indiana Utility Regulatory Commission (IURC)
not re-checked