2026-07-28PJM and its transmission owners ask FERC to pause the large-load show-cause proceeding 2 src
Federal Energy Regulatory Commission · PJM Interconnection
reported
2026-06-18FERC issues Federal Power Act Section 206 show-cause orders to all six RTOs/ISOs on large-load interconnection — RM26-4-000 rulemaking itself remains un-acted-on 6 src
Federal Energy Regulatory Commission · Chris Wright · Department of Energy · Laura Swett
reported
2026-04-16FERC misses DOE-ordered April 30 deadline on large-load interconnection Docket RM26-4-000 — issues Intent to Act order committing to June 2026 action 6 src
Federal Energy Regulatory Commission · Chris Wright · Department of Energy · Laura Swett
confirmed
2025-06-20Texas Gov. Abbott signs SB 6 — large-load (≥75 MW) interconnection reform; mandatory remote-disconnect / curtailment for entrants post Dec 31 2025; bellwether state model for the federal FERC ANOPR 6 src
Greg Abbott · Public Utility Commission of Texas · ERCOT · Texas Legislature
confirmed