Tag index

#Interconnection

Events indexed under #Interconnection — 3 entries in the record.

3 events From Oct 23, 2025 To Jun 18, 2026 Open in filter view →
DateEventLanesStatus
2026-06-18FERC issues Federal Power Act Section 206 show-cause orders to all six RTOs/ISOs on large-load interconnection — RM26-4-000 rulemaking itself remains un-acted-on 6 src
Federal Energy Regulatory Commission · Chris Wright · Department of Energy
reported
2026-04-16FERC misses DOE-ordered April 30 deadline on large-load interconnection Docket RM26-4-000 — issues Intent to Act order committing to June 2026 action 6 src
Federal Energy Regulatory Commission · Chris Wright · Department of Energy
confirmed
2025-10-23Energy Secretary Wright invokes rare DOE-over-FERC directive authority to compel ANOPR on large-load interconnection — Docket RM26-4-000 — final action ordered by April 30 2026 6 src
Chris Wright · Federal Energy Regulatory Commission · Department of Energy
confirmed