| Date | Event | Lanes | Status |
|---|
| 2026-09-21 | Residents and One Hundred Miles Sue Effingham County Development Authority Over Closed-Door OpenAI Data Center Deal
3 src OpenAI, Southern Environmental Law Center | | reported |
| 2026-08-19 | Oracle Drops Wisconsin PSC Suit, Leaving $100M-Plus Annual Collateral Requirement for Port Washington Campus
4 src Oracle, Wisconsin Public Service Commission, We Energies, OpenAI | | not re-checked |
| 2026-08-13 | Attorney Challenges Oracle/OpenAI $43B Saline Township Tax Break, Arguing Township Skipped Required Public Hearing
3 src Oracle, OpenAI | | not re-checked |
| 2026-08-12 | Louisiana PSC Votes 3-1 to Let Meta Hide Electricity Demand Data for $50B Hyperion Campus
3 src Meta Platforms, Sierra Club | | not re-checked |
| 2026-08-11 | Wisconsin PSC Forces ATC to Restart $1.7B Port Washington Data Center Grid Application; FERC Gap Leaves Ratepayer Cost-Shift Unresolved
2 src Wisconsin Public Service Commission, We Energies | | not re-checked |
| 2026-08-04 | Effingham County GA Commissioners Pass Industrial-Zoning Ordinance With Project Camellia Off the Agenda
7 src OpenAI | | reported |
| 2026-08-03 | Gov. Abbott Freezes Texas Data Center Grid Connections, Orders ERCOT/PUCT Audit
3 src Greg Abbott, ERCOT, Public Utility Commission of Texas, Meta Platforms and 4 more | | not re-checked |