| Date | Event | Lanes | Status |
|---|
| 2026-06-17 | IURC Order in Cause 46322 Approves NIPSCO-Amazon Special Contract and NIPSCO-GenCo PPA on a Partial Settlement; Pricing Terms Held Confidential
3 src Indiana Utility Regulatory Commission (IURC), NIPSCO, NIPSCO Generation LLC (GenCo) | | reported |
| 2025-11-19 | IURC Reaffirms GenCo Approval and Amazon Special Contract Framework; NIPSCO Announces $7B, 2.6GW Gas + 400MW BESS Build for Amazon
5 src NIPSCO, NIPSCO Generation LLC (GenCo), Amazon Web Services, Indiana Utility Regulatory Commission (IURC) | | not re-checked |
| 2025-09-24 | Indiana IURC Approves NIPSCO GenCo as First U.S. Limited-Regulation Utility Affiliate for Data Center Generation (Cause 46322)
5 src NIPSCO, NIPSCO Generation LLC (GenCo), Indiana Utility Regulatory Commission (IURC) | | not re-checked |
| 2025-07-24 | DOE selects four federal sites for AI datacenter buildout — Idaho National Laboratory, Oak Ridge Reservation, Paducah Gaseous Diffusion Plant, Savannah River Site — implementing Section 3 of the July 23 EO
5 src Chris Wright, Department of Energy |
| not re-checked |
| 2025-07-23 | Trump signs Executive Order 'Accelerating Federal Permitting of Data Center Infrastructure' — 100 MW threshold, NEPA categorical-exclusion creation directive, <50% federal-financial-assistance carve-out from NEPA 'major Federal action'
7 src Donald Trump, Howard Lutnick, Chris Wright, Doug Burgum and 5 more |
| reported |