| Date | Event | Lanes | Status |
|---|
| 2026-10-12 | DOE emergency orders keep plants online: latest quarterly renewals and a PJM heat-event order, through October 2026
1 src Department of Energy, Chris Wright |
| reported |
| 2026-09-11 | D.C. Circuit vacates DOE's Campbell coal-plant emergency order; DOE seeks rehearing en banc
3 src Department of Energy | | reported |
| 2026-06-18 | FERC issues Federal Power Act Section 206 show-cause orders to all six RTOs/ISOs on large-load interconnection — RM26-4-000 rulemaking itself remains un-acted-on
6 src Federal Energy Regulatory Commission, Chris Wright, Department of Energy, Laura Swett |
| reported |
| 2026-05-01 | DOE §202(c) emergency coal-retention order log through May 2026: 43+ orders, ~4.4 GW stalled across 6 plants, D.C. Circuit challenges filed
10 src Chris Wright, Department of Energy, NIPSCO, Earthjustice and 1 more |
| reported |
| 2026-04-16 | FERC misses DOE-ordered April 30 deadline on large-load interconnection Docket RM26-4-000 — issues Intent to Act order committing to June 2026 action
6 src Federal Energy Regulatory Commission, Chris Wright, Department of Energy, Laura Swett |
| not re-checked |
| 2025-10-23 | Energy Secretary Wright invokes rare DOE-over-FERC directive authority to compel ANOPR on large-load interconnection — Docket RM26-4-000 — final action ordered by April 30 2026
6 src Chris Wright, Federal Energy Regulatory Commission, Department of Energy |
| not re-checked |
| 2025-07-24 | DOE selects four federal sites for AI datacenter buildout — Idaho National Laboratory, Oak Ridge Reservation, Paducah Gaseous Diffusion Plant, Savannah River Site — implementing Section 3 of the July 23 EO
5 src Chris Wright, Department of Energy |