#Doe

Events indexed under #Doe — 5 entries in the record.

5 events From Jul 24, 2025 To Jun 18, 2026 Open in filter view →
Activity over time Events per year
2025 · 2 events2026 · 3 events20252026
DateEventLanesStatus
2026-06-18FERC issues Federal Power Act Section 206 show-cause orders to all six RTOs/ISOs on large-load interconnection — RM26-4-000 rulemaking itself remains un-acted-on 6 src
Federal Energy Regulatory Commission · Chris Wright · Department of Energy · Laura Swett
reported
2026-05-01DOE §202(c) emergency coal-retention order log through May 2026: 43+ orders, ~4.4 GW stalled across 6 plants, D.C. Circuit challenges filed 10 src
Chris Wright · Department of Energy · NIPSCO · Earthjustice · +1
reported
2026-04-16FERC misses DOE-ordered April 30 deadline on large-load interconnection Docket RM26-4-000 — issues Intent to Act order committing to June 2026 action 6 src
Federal Energy Regulatory Commission · Chris Wright · Department of Energy · Laura Swett
confirmed
2025-10-23Energy Secretary Wright invokes rare DOE-over-FERC directive authority to compel ANOPR on large-load interconnection — Docket RM26-4-000 — final action ordered by April 30 2026 6 src
Chris Wright · Federal Energy Regulatory Commission · Department of Energy
confirmed
2025-07-24DOE selects four federal sites for AI datacenter buildout — Idaho National Laboratory, Oak Ridge Reservation, Paducah Gaseous Diffusion Plant, Savannah River Site — implementing Section 3 of the July 23 EO 5 src
Chris Wright · Department of Energy
confirmed