Beale Infrastructure (Blue Owl) breaks ground on $1B Project Clydesdale data center campus in Owasso, Oklahoma

confirmed Importance 6/10 ~2 min read 2 sources 1 actor

Opening

Beale Infrastructure, the Blue Owl Capital portfolio company, broke ground on October 30/31, 2025 on Project Clydesdale — a $1 billion data center campus in Owasso, Tulsa County, Oklahoma (northeast of Tulsa). The 506-acre site is Beale’s first completed groundbreaking in Oklahoma and was announced via BusinessWire on October 31, 2025.

What Happened / Key Facts

Project Clydesdale occupies 506 acres in Owasso, Oklahoma. The campus consists of at least one phase with three possible additional phases; each phase covers approximately 200,000 square feet. Construction is expected to take at least five years. The project represents a $1 billion capital investment and will generate approximately 100 permanent high-paying technical roles plus thousands of local construction jobs during build-out. Projected tax revenue: $2 million annually to Tulsa County and Owasso Public Schools once operational. Tenant information was not disclosed publicly.

Broader Context

The Clydesdale groundbreaking preceded Beale’s other Oklahoma proposals (Project Mustang in Claremore; the subsequently-withdrawn Project Atlas in Coweta). As of March 2026, Oklahoma Energy Today reported that Blue Owl Capital’s financial challenges (stock crashed 68% from peak; active BDC redemption crisis) could affect Oklahoma datacenter project timelines — though no specific Clydesdale delays were confirmed at that time. Clydesdale appeared to remain under construction as of June 2026.

  • beale-infrastructure — developer org profile
  • blue-owl-capital — parent company
  • 2026-04-29–beale-infrastructure-breaks-ground-de-soto-ks-datacenter — parallel De Soto project (more significant for procurement overlap thesis)

Sources & Citations

Tiers Tier 1 court records & gov docs · Tier 2 established outlets · Tier 3 regional & specialty press · Tier 4 opinion or single-source. Methodology →
Cite this entry
The Cascade Ledger. “Beale Infrastructure (Blue Owl) breaks ground on $1B Project Clydesdale data center campus in Owasso, Oklahoma.” The Capture Cascade Timeline, October 31, 2025. https://capturecascade.org/event/2025-10-31--beale-infrastructure-project-clydesdale-groundbreaking-owasso-ok/